Fourteen Years On, Kenya Starts Drilling for Oil — but the Deadline Is Already Tight
After fourteen years of waiting, Kenya has started drilling for oil.
On Friday, November 20, 2026, Energy and Petroleum Cabinet Secretary Opiyo Wandayi presided over the spudding of the Amosing 1 well pad in the South Lokichar Basin, Turkana County — switching on the GW70 onshore rig, a 1,500-horsepower unit leased from China's Great Wall Drilling Company, which arrived at the Port of Mombasa in September aboard the MV Transit Sedanka from Duqm, Oman. It is the first well of Gulf Energy E&P BV SEZ's US$6 billion programme in Blocks T6 and T7, and the first commercial drilling Kenya has ever undertaken.
Here is the plan. First commercial production is set for December 1, 2026, when President William Ruto will flag off the first oil convoy from South Lokichar and unveil the crude's official trading name — chosen by public participation in October from four shortlisted names: Great Rift Light, Great Rift Intermediate, Great Rift Blend and Great Rift Sweet. Phase one, running from 2026 to 2032, targets 20,000 barrels per day from the NEAT fields — Ngamia, Amosing, Twiga and Ekales — with a best-estimate recovery of 326 million barrels over a 25-year contract period. Output is to rise to 50,000 barrels a day from the end of 2032, with a long-term target of 120,000.
The logistics are as big as the numbers. Crude will be trucked by road to Mombasa — about 600 trucks — and stored at the Kenya Petroleum Refineries Limited tank farms. The first export shipment is expected on March 1, 2027, and rail transport is planned for phase two. If the schedule holds, Kenya would join Uganda and South Sudan as an East African oil exporter.
The history behind the ceremony is a lesson in how long oil takes. Crude was first discovered in Turkana in 2012. Tullow Oil, the original developer, walked away. Gulf Energy took over under production sharing contracts and a parliament-ratified Field Development Plan. Fourteen years passed between discovery and the first drill bit turning — years in which Turkana heard promises, saw a developer leave, and waited for another to arrive.
But watch the calendar, because the plan already has a problem built into it. Drilling only started on Friday, November 20, and an onshore well takes at least two weeks to lift first volumes — so first volumes would land around December 4, after the December 1 target. The December 1 date is the government's stated target, not a certainty. That is not a prediction of failure; it is arithmetic. The ceremony happened on schedule. The geology will keep its own schedule.
That tension — between a political date and a technical one — is the story of this project in miniature. The December 1 flag-off is a set piece: a president, a convoy, a name unveiled for the cameras. The name itself was chosen by public participation, and the four options all carry the same message — Great Rift, the geography Kenya wants the world to associate with its crude, the way Uganda named its own Pearl Sweet. A trading name is a small thing, but it is also a declaration: Kenya intends to sell this oil on the world market, not just burn it at home.
The bigger questions sit behind the ceremony. Twenty thousand barrels a day is a modest start by world standards, but for Kenya it would be a first — a new export, a new revenue line, and a test of whether the country can manage a resource its neighbours have fought over. The 326 million barrels under the NEAT fields is a best estimate, not a guarantee, and the history of African oil is full of estimates that shrank once production began. The trucks to Mombasa are a stopgap; the rail link planned for phase two is the infrastructure that would make the project durable. And Turkana itself — the county that has waited fourteen years — will be watching whether the jobs, the roads and the revenue reach the people who live above the oil, or only the balance sheet in Nairobi.
None of that diminishes what happened on Friday. A rig that arrived from Oman in September is now turning in Turkana soil. A project that lost its first developer has a second one drilling. And a country that found oil in 2012 is, at last, producing a date — December 1 — that can be tested against reality within a fortnight.
The test comes quickly. If the first convoy rolls out on December 1 as promised, Kenya will have its oil moment. If it slips to December 4 or beyond, the question will not be whether Kenya has oil — fourteen years of geology have settled that. It will be whether, this time, the deadline holds.